File #: 25-1400    Version: 1 Name:
Type: Amendment Status: Passed
File created: 10/28/2025 In control: Board of County Commissioners
On agenda: 11/18/2025 Final action: 11/18/2025
Title: Agreement Amendment / CDBG MT041 King and Baker Drainage Project time extension.
Attachments: 1. MT041-A2

 

Consent Agenda                      Quasi-Judicial Public Hearing

Regular Business                      3:00 pm

Public Hearing                     Amendment

 

DEPARTMENT:                       Administration

SUBMITTED BY:                     Dennis Johnson

PRESENTED BY:                     Dennis Johnson

 

 

TITLE & DESCRIPTION:

title

Agreement Amendment / CDBG MT041 King and Baker Drainage Project time extension.

body

 

REQUESTED MOTION:

To approve the Community Development Block Grant (CDBG) Project Agreement MT041 Amendment Two with the Florida Department of Commerce, as presented, and authorize the County Administrator to execute the Amendment.

 

SUMMARY:

The County has requested an extension of the grant completion date to February 13, 2027, to more accurately reflect the project schedule. In addition, the County has requested that the Deliverables and Tasks be revised to better align with the actual pace of the project.

 

BACKGROUND:

DeSoto County has been awarded $3,757,012.00 in CDBG-MIT funding for mitigation efforts to overhaul the current decaying King and Baker drainage system.

 