TITLE & DESCRIPTION:
title
Change Order/Housing Demolition Reconstruction
body
REQUESTED MOTION:
To approve the change order as presented.
SUMMARY:
This change order is to replace a 26 gallon pressure tank. The original work write up did not include a replacement of the tank as it was not known to need replacement at the time. The Contractor and Building inspector both recommend replacement. This change order will come from SHIP and HHRP funds.
BACKGROUND:
Durning rehabilitation of homes there are times when unexpected issues arise. The Board of County Commissioners can approve change orders they deem necessary to complete the project.
FUNDS:
Budget Amount: $165,000
Actual Agenda Item: $165,761.
Cost: $861.
Account Number: 141-71265543400000
Explanation: Change order