Title: Change Order/Housing Demolition Reconstruction
Attachments: 1. Change order.jpg, 2. Work Write UP.pdf

 

Consent Agenda                      Quasi-Judicial Public Hearing

Regular Business                      9:00 am

Public Hearing                     Amendment

 

DEPARTMENT:                       Social Services

SUBMITTED BY:                     Lauri Benson

PRESENTED BY:                     Lauri Benson

 

 

TITLE & DESCRIPTION:

title

Change Order/Housing Demolition Reconstruction

body

 

REQUESTED MOTION:

To approve the change order as presented.

 

SUMMARY:

This change order is to replace a 26 gallon pressure tank. The original work write up did not include a replacement of the tank as it was not known to need replacement at the time. The Contractor and Building inspector both recommend replacement. This change order will come from SHIP and HHRP funds.

 

BACKGROUND:

Durning rehabilitation of homes there are times when unexpected issues arise. The Board of County Commissioners can approve change orders they deem necessary to complete the project.

 

FUNDS:

Budget Amount: $165,000

Actual Agenda Item: $165,761.

Cost: $861.

Account Number: 141-71265543400000

Explanation: Change order