☐ Consent Agenda ☐Quasi-Judicial Public Hearing
☒ Regular Business 9:00 am
☐ Public Hearing Change Order
DEPARTMENT: Administration
SUBMITTED BY: Megan Deuchar
PRESENTED BY: Dennis Johnson
TITLE & DESCRIPTION:
title
Contract Change Order #1 / Construction Services for C.R. 769 Bridge over Horse Creek
body
REQUESTED MOTION:
Approve the Contract Change Order #1 with Viking Diving Services, Inc., for additional construction services associated with the C.R. 769 Bridge over Horse Creek project, contingent upon approval by Florida Commerce.
SUMMARY:
Staff is requesting approval of Contract Change Order #1 with Viking Diving Services, Inc., for additional construction services associated with the C.R. 769 Bridge over Horse Creek project.
BACKGROUND:
During construction, after exposing the piles at Bents 12, 13, and 14, the contractor identified additional concrete scaling that was not visible during initial inspections. To address this deterioration and protect the piles from further environmental degradation, the Change Order adds 120 linear feet of non‑structural pile jacketing, totaling 12 jackets. The additional scope also includes the required mobilization and maintenance of traffic to complete the work.
This Change Order increases the contract amount by $108,500.00 and adds 31 days to the construction schedule, consisting of 30 days for the added work and one previously recognized weather day. The new contract completion date is November 17, 2026.
The original contract for this project was approved by the Board and is funded by the Florida Commerce Community Development Block Grant Mitigation (CDBG‑MIT) Program. This Change Order is contingent upon approval by Florida Commerce.
FUNDS:
Budget Amount: $2,797,180.00
Actual Agenda Item: $108,500.00
Cost: $1,830,759.28
Account Number: 308-60555416300000
Explanation: Cost reflects the new contract amount including Change Order #1.